Placing of formwork for the basement walls continues. It is possible to see the size shape of the floor plan, now. The basement will house the garage (the location of the garage door is not visible, yet), as well as conditioned space. At the left rear, the break in the wall will be the location of doors which provide a walk-out to the back yard.
There is good weather now, but we are expecting a wetter-than-normal fall and winter, so it is important to get the basement done quickly and avoid having a hole filled with water.
The excavated area at the lower right will be where the driveway descends.
No comments:
Post a Comment