House on the Coast, Post #4

The contractor is wasting no time in moving ahead with framing. This photo was taken on Friday afternoon:


Because this project has a an accelerated construction schedule, the steel contractor had begun fabricating the beams and columns well ahead of time, allowing them to be assembled immediately after the foundation was poured.

Since the last post, waterproofing has been applied to the exterior of the basement walls, visible as the black areas. The majority of the structural steel is in place, providing a large clear space for the garage, seen at the right-rear portion of the house. Most of the remaining area is framed conventionally, in wood. The corrugated steel pans at the right side will support poured-concrete patio areas, and the frames extending above the foundation support a second-floor deck over a large first-floor loggia.

The next major task is to set floor joists and sheathing on the first floor.